Log from 11.03-2021. Showing biggest repairs and maintenance done.


11.03-2021:
•All hydraulic hoses along main boom (flow for jib) swapped due to cracking in coating in which had caused hose armour to rust. Hoses in this condition it's better to change sooner rather than later as the lifespan is quite uncertain.

02.06-2021:
•Annual crane control and change of an hydraulic tube and fitting that continued to come loose lately. In addition the front support legs had a change of 1 hose each (due to rubbing against metal), for the crane to be approved.